In the summer of 2006, WUOT completed the second phase of the digital conversion process: upgrading our control room and production studios to digital and installing the new "Content Depot" system, the mechanism which allows WUOT to retrieve and broadcast programming from the public radio satellite.
Click here to see the final drawings for the project.
Click on a link below to view the work as it was in progress.
Main Control Room
Production Studio No. 1
Production Studio No. 2
Equipment Room and Talk Studio
Main Control Room progress photos:

The "temporary" main control room was located in what was a conference room in the suite. WUOT's engineer, Mike Murrell, along with assistant Kevin Potter, disassembled the original control room and reassembled it here in less than two days!
Pictured above, WUOT's main on-air control room before April 10, 2006....

....after April 10!

Another view of gutted control room.
April 21: Re-building the Control Room floor, one view...
...and another view.

April 31: Carpet installed in Main Control Room. (above)

May 5: Main Control Room: New furniture installation begins.
Control Room on Monday, May 8, 2006
As of June 12, 2006

Done! June 29, 2006

Photo taken 10/06